On Monday, 19 June, LHC operation was paused for one week to allow the technical teams to carry out preventive and corrective maintenance on the machine and its subsystems
The AD operations team received on Friday, 1 June – 12 days earlier than rescheduled – the green light from the AD injection kicker expert: beam could be injected again in the AD ring
On 11 May, four days before the original schedule had set a target of 1200 bunches per beam, the LHC made its final intensity ramp-up step to 2400 bunches per beam
The beam commissioning of the Antiproton Decelerator will start on 12 June, and the aim is to deliver antiprotons to the eagerly waiting AD-ELENA experiments on 30 June
Another important milestone was achieved in the LHC beam commissioning: on 21 April, the LHC Engineer in Charge declared “stable beams” at 6.8 TeV, the first time in 2023
With the progressive recommissioning of the injectors – including, now, the SPS – the various types of beam are being set up and are gradually reaching the downstream accelerators
The last LHC beam of 2022 was dumped in the early morning of Monday, 28 November; 17 weeks later, on Monday, 27 March 2023, we plan to inject the first beam of the year into the LHC